Routine Generator Test

Scheduled for Thursday 6th February 2020 at 11:00 (London)

Schedule/description of work

Our data centre will be performing a routine generator test, during this window services will be at a marginal risk. They will simulate a full mains failure and fully test their backup systems. All sensing and switching is performed by their automatic systems with critical load sustained by the UPS's during the changeover periods, they will retain the ability to revert to mains power immediately if needed. There is a marginally increased risk during this period and the situation will be constantly monitored by their operations team.

Scheduled start time
February 06, 2020 11:00
Duration
4 hours
Status
Finished